Project Timeline

(updated 26 Mar 15)

2010
March: Excavate Devonshire Tunnel northern portal - complete

2011
January-March: Surface Linear Park from Devonshire Tunnel to Network Rail bridge – complete

2012
April: Bridge installation over Monksdale Road - complete 

2013
January: Devonshire Tunnel, Lyncombe Vale, Combe Down Tunnel, Tucking Mill Viaduct - main works complete.
 
February: Bridge installation over Millmead Road - complete

February: Bloomfield Road Open Space - New path in place and open to the northern section of the route - complete

February-March: Midford Castle path works - complete

6 April: Celebration opening event

November-December: Link via Lower Bristol Road and Fieldings Road Bridge to Riverside Towpath: widening the foot-way on the Lower Bristol Road south side.

2014

February: Installation of ‘Share the Path’ thermoplastic surface-fixed signs

February-April: Re-opening of the Network Rail bridge over the main-line Bath-Bristol railway

February-April: Surfacing of the Bellotts Road stretch
March-July: Claude Avenue bridge ramp installation

April: Installation of Toucan Crossing on Lower Bristol Road

May: Two artworks (UTurnRound Device and Geology Board) installated in Combe Down Tunnel cutting.

June: Midford Castle stretch – installation of catch-fencing on the south side of steep embankment  

September: Claude Avenue Bridge access ramp opens

2015


March: Picnic tables at north and south end of Combe Down Tunnel installed